Stars' End : version 4.0 : progess, west elevation
[
details
|
east
|
north
|
loft
|
garage
|
tree
]
15 January 2000 -- loft stairs
14 November 1999 -- kitchen floor
17 October 1999 -- fake beams
2 October 1999 -- scaffolding dropped
18 September 1999 -- artexed
11 September 1999 -- rendered and guttered
21 August 1999 -- roof tiling (all but) finished
13 August 1999 -- roof tiling restarts
17 July 1999 -- chimney and final window
10 July 1999 -- roofing starts
3 July 1999 -- gables and windows
19 June 1999 -- roof trusses
12 June 1999 -- walls up to roof level
5 June 1999 -- internal upper walls
29 May 1999 -- some upper walls
22 May 1999 -- first floor
15 May 1999 -- higher walls
8 May 1999 -- a little bit of scaffolding
1 May 1999 -- most of the ground floor wall
24 April 1999 -- our first wall
17 April 1999 -- ground floor
10 April 1999 -- 4 courses of bricks
6 April 1999 -- groundbeams
27 March 1999 -- trenches
14 March 1999 -- piling finishes
27 February 1999 -- piling starts
15 January 1999 -- topsoil stripped
20 December 1998 -- pre build